OPERATOR'S PMCS -cont
2-9. START-UP PROCEDURES.

TM-5-4310-393-14 Air Compressor Diesel Engine Driven 20 CFM 3200 PSI Model KA7-DA Manual
Page Navigation
  13    14    15    16    17  18  19    20    21    22    23  
TM 5-4310-393-14 a. Inspection.  Inspect the unit for damage.  Report all discrepancies in accordance with DA PAM 738-750 b. Preparation.  Remove  the  tarpaulin  or  protective  cover  from  the  unit.    Verify  that  the  assembly  clamping  devices are in place and in good condition.  Insert the filter cartridge into the purification cylinder.  (paragraph 3-16.2).  Ensure that pipes,  hoses  and  connections  are  securely  in  place.    Place  the  compressor  and  engine  units  in  the  proper  position  for assembly  by  aligning  the  V-belt  grooves  in  the  engine  and  compressor  pulleys.    When  the  sections  are  aligned  use  the draw latches to clamp the units together (Figure 1-1 and 1-2 ). 1. Make  sure  all  draw  latches  holding  the  two  units  together  are  securely  in  place  in  the  fully  locked-down position.  (Figure 1-1 and Figure 1-2). 2. Remove the engine unit V-belt guard by unbolting seven bolts and lifting belt guard from frame. 3. Set decompression lever to FREEWHEEL position.  (Figure 4-3) WARNING TO  AVOID  PERSONAL  INJURY,  AVOID  TRAPPING  FINGERS  BETWEEN  V-BELT AND PULLEY WHILE INSTALLING V-BELT. 4. Ensure V-belt is in compressor pulley groove, then place V-belt in groove on top of engine pulley, and Insert flat  of  screwdriver  between  belt  and  sheave  at  2700  position.    Keeping  screwdriver  perpendicular  to  sheave  rotate  left (ccw) until belt seats in sheave groove. 5. Reinstall the engine unit V- belt guard. c. Location The site location must be free of contaminated air.  A sufficient supply of fresh air for properly cooling the units must be available.  The unit must be located at least 20 inches away from any wall and away from other machinery for  proper  cooling  The  combined  compressor  unit  should  be  placed  on  a  firm,  level  surface.    Under  no  circumstance should the compressor be operated if tilted more than 15 degrees in any direction. WARNING TO  ENSURE  AS  LITTLE  AIR  CONTAMINATION  AS  POSSIBLE,  THE  INTAKE  HOSE MUST   BE   FULLY   EXTENDED   AND   ALWAYS   BE   LOCATED   UPWIND   OF   THE ENGINE EXHAUST.  WHEN THE WIND CHANGES, THE COMPRESSOR AIR INTAKE MUST   BE   RELOCATED.      THIS   ACTION   IS   IMPERATIVE   TO   ENSURE   THAT   AS LITTLE CONTAMINATED AIR AS POSSIBLE ENTERS THE COMPRESSOR. 2-8.  PRE-OPERATIONAL CHECKS. a. Ensure the compressor intake hose is fully extended and located upwind of the engine exhaust. b. Check oil level in compressor (paragraph 3-5.4). 2-8







Western Governors University

Privacy Statement
Press Release
Contact

© Copyright Integrated Publishing, Inc.. All Rights Reserved. Design by Strategico.