4-59. INSTRUMENT PANEL REPLACEMENT.
This Task Covers:
a.
Removal
b.
Installation
Initial Setup:
Equipment Conditions:
Equipment Conditions (Cont):
Engine coolant temperature gage removed (see
Cold start valve removed (see paragraph 4-77).
paragraph 4-76).
ON/OFF engine switch removed (see para-
Engine oil pressure gage removed (see para-
graph 4-56).
graph 4-80).
Master battery switch removed (if removing bracket)
Ammeter removed (see paragraph 4-58).
(see paragraph 4-54).
Tach/hourmeter removed (see paragraph 4-77).
Fuse and fuse holder removed (see paragraph 4-
57).
Air pressure gage removed (see paragraph 4-78).
Air compressor discharge temperature gage re-
Materials/Parts:
moved (see paragraph 4-79).
Eight lockwashers
Engine override and engine start button removed
(see paragraph 4-55).
Tools/Test Equipment:
Ether start kit removed (see paragraph 4-38).
General mechanic's tool kit
a.
REMOVAL
1. Remove four nuts (2), lockwashers (3), flatwashers (4), and instrument panel (1) from four vibration Isolators (12).
Discard lockwashers.
2. Remove four nuts (11), lockwashers (10), and vibration Isolators (12) from bracket (5). Discard lockwashers.
3. If damaged, remove four nuts (9), lockwashers (8), bolts (6), and bracket (5) from fender (7). Discard
lockwashers.
b.
INSTALLATIONI
1. If removed, Install bracket (5) on fender (7) with four bolts (8), new lockwashers (8), and nuts (9).
2. Install four vibration Isolators (12) on bracket (5) with four new lockwashers (10) and nuts (11).
3. Install instrument panel (1) on four vibration Isolators (12) with four flatwashers (4), new lockwashers (3), and nuts
(2).
4-126