STEP 1. OPEN THE RECEIVER VALVE (IF THE RECEIVER IS TO BE USED).
STEP 2. START THE ENGINE (SEE FIG. 2-3).
STEP 3. ALLOW THE COMPRESSOR TO OPERATE UNTIL THE RECEIVER
PRESSURE GAGE INDICATES SUFFICIENT PRESSURE TO CHARGE
THE EQUIPMENT (IF THE RECEIVER IS TO BE USED).
STEP 4. ADJUST THE PRESSURE REGULATING VALVE FOR REQUIRED
DELlVERY PRESSURE. OBSERVE THE HIGH PRESSURE GAGE
FOR PRESSURE EXCEEDING 600 PSIG.
STEP 5. CONNECT THE AIR HOSE AND CHUCK ASSEMBLY TO THE
PRESSURE OUTLET AND THE EQUIPMENT TO BE CHARGED.
STEP 6. SLOWLY OPEN THE OUTLET VALVE.
STEP 7. PRESS AND HOLD THE PUSH VALVE FOR A PERIOD OF FIVE
(5) SECONDS AT FIFTEEN (15) MINUTE INTERVALS WHILE OPERATING
THE COMPRESSOR, TO ENSURE EFFECTIVE FILTERING ACTION.
TSO14359