SECTION VI. PREPARATION FOR STORAGE OR SHIPMENT
2-29.
Administrative storage of equipment issued to and used by Army activities will have preventive maintenance
performed in accordance with the Preventive Maintenance Checks and Services (PMCS) charts before storing. When
removing the equipment from administrative storage, the PMCS should be performed to ensure operational readiness.
Use the following steps for repacking the compressor or components for shipment or storage.
a.
Place all loose items in a plastic bag and secure the bag to the component removed.
b.
Place protective connector covers on all connectors.
c.
Securely crate the component to prevent damage during movement.
d.
Do not store with or near corrosive materials.
2-60