TM 5-4310-373-14
AlR TANK SYSTEM
MAINTENANCE SUMMARY. This task covers:
The inspection, removal and installation of the safety valve, safety interstage valve, check valve, pressure gage, drain cock,
and shutoff valve. This test also includes the removal and installation of the air tank.
INITIAL SETUP
Personnel Required
General Safety Instructions
1
Discharge air in tank before removal of components.
Disconnect main power.
TASK SUMMARY
NO.
TASK
REFERENCE
REMARKS
1
Safety valve, inspection, removal,
installation
2
Safety interstage valve, inspection,
removal, installation
Check valve, inspection, removal,
3
dissasembly, assembly, installation.
4
Pressure gage, inspection, removal,
installation
5
Drain cock, inspection, removal,
installation
6
Shutoff valve, inspection, removal,
installation
7
Air tank removal, installation
4-71