TM 5-4310-373-14
4-50. AlR TANK REMOVAL/INSTALLATION
This task covers:
The removal and installation of the air tank.
INITIAL SETUP
Equipment Condition:
Tools:
Main power OFF
Air in tank discharged
Materials/Parts:
As required
Personnel Required:
Approximate Time Required (minutes):
120
1 Mechanic
REMARKS
LOCATION/lTEM
ACTION
Figure 4-90 will aid you in
locating components that are
directly attached to air tank.
Disconnect.
1. Main power
Open.
2. Drain cock (3)
Remove.
3. Belt guard assembly
Remove.
4. Motor starter
Remove.
5. Motor
Remove.
6. Tubing assemblies
Remove.
Remove.
8. Pressure switch
Remove
9. Pressure gage (1)
Remove.
10. Safety valve (2)
Remove.
11. Drain cock (3)
Remove.
12. Air hose (4)
Remove.
13. Pipe fitting (5)
Remove.
14. Bushing (6)
Remove
15. Shutoff valve (7)
Remove.
16. Nipple (8)
Be careful not to damage threads.
Remove.
17. Check valve (9)
4-82