TM 9-4310-397-14
SECTION III OPERATOR'S MAINTENANCE PROCEDURES
3-7. GENERAL.
With the exception of service and inspection procedures noted in the PMCS Table 2-1, the following procedure is the
only maintenance procedure authorized to the operator by the MAC.
3-8. CLEANING.
This task covers:
a.
Cleaning
INITIAL SETUP
Equipment Conditions:
Air compressor shutdown. (See para 24, c.)
Doors open as necessary.
Cleaning.
(1)
Mix a small quantity of detergent (item 6, section II, appendix E) with clean water to make a wash solution.
(2)
Dampen a rag (item 2, section II, appendix E) with wash solution and clean the equipment.
(3)
Dampen a rag (item 2, section II, appendix E) with clean water and rinse the equipment. Rinse rag in
clean water and continue until all detergent residue has been removed.
(4)
Wipe the equipment with a clean dry rag (item 2, section II, appendix E) until it is thoroughly dry.
3-5/(3-6 blank)