TM 5-4930-218-14
Section Ill. FRAME
d. Remove air reservoirs, air chamber and master
cylinder assemblies, service hoses and tubing, relay
The trailer frame is an all-steel welded assembly
consisting of two parallel frame rails with cross-
members between the rails. Frame weldment also in-
cludes landing gear bracket, spring hanger brackets,
lifting bars, and two upper halves of the axle bearing
housing welded to the frame rails.
9-11. Cleaning and Inspection
a. Clean the frame assembly with dry cleaning
solvent (fed. spec. P-D-680) and dry thoroughly.
a. Remove four nuts, lock washers and bolts
b. Inspect the frame for cracks, breaks, broken
securing skid-mounted lubricating and servicing unit
welds, and other damage.
to trailer frame. Lifting rings are provided at four
c. Straighten minor bends and reweld any broken
places on the top of the enclosure. Using suitable lift-
welds.
ing equipment, lift unit off trailer frame.
through 4-55).
Installation is essentially the reverse of removal.