4-40. CENTRIFUGAL UNLOADER/lNSPECTION/CLEANING
This task covers:
The inspection and cleaning of the centrifugal unloader assembly.
INITIAL SETUP
Tools:
Equipment Condition:
Centrifugal unloader removed
Materials/Parts:
C o m p r e s s e d Air
Drycleaning Solvent P-D-680
Personnel Required:
Approximate Time Required (minutes):
1 Mechanic
15
LOCATION/lTEM
ACTION
REMARKS
I
Figure 4-68. Centrifugal unloader assembly
1. All metal parts
Inspect for cracks.
Replace if cracked.
2. Plunger (1)
Inspect for free movement.
Replace if cleaning is not effective.
3. Springs (2) and (3)
Inspect for lost tension or
Replace if defective.
broken.
4. Ball (4)
Inspect for pitting.
Replace if pitted.
5. Body (5) and (6)
Inspect for thread damage.
Replace if damaged.
6. Felt (7)
Replace.
7. Screen (8)
Inspect for plugged holes or
Replace if necessary.
corrosion.